Getting financing

What Does a Construction Work-in-Progress Report Tell a Lender?

A work-in-progress report, often called a WIP report, shows how each construction job is moving financially. It compares what the contract is worth, the cost of work completed, how much has been billed and what it may cost to finish.

By
Alexander Schnavel
Reviewed by
Published
November 11, 2026
Last reviewed
Key points

A work-in-progress report, often called a WIP report, shows how each construction job is moving financially. It compares what the contract is worth, the cost of work completed, how much has been billed and what it may cost to finish. A lender or surety may use it to understand whether a contractor has enough money and control over its projects to meet upcoming bills.

Why isn't a profitable contract the same as available cash?

A project can look profitable on paper while using up the contractor's cash. Workers may have been paid, materials delivered and expenses recorded, but the customer has not yet approved or paid the next progress invoice. A WIP report helps reveal that timing gap and whether costs are beginning to exceed the original estimate.

It also helps separate three different amounts: work performed, invoices sent and cash collected. Those numbers are not interchangeable. A contractor that has completed $400,000 of work may have billed only $300,000, and may have received even less in its bank account.

What belongs in the report?

A useful project-by-project schedule starts with the job name and current contract price, including approved changes. It records costs incurred so far, the newest estimate of total costs, estimated cost still to finish, progress billed, payments received, projected gross profit and expected completion date. Keep pending change orders separate until their status is clear.

The Surety Association of Canada lists a regular WIP schedule among the documents a surety may request, including contract price, changes, amounts billed, costs incurred, cost to complete, estimated gross profit and completion date. Different reviewers can require different formats. [1]

Example: one job with a billing gap

Imagine a $500,000 project with an expected total job cost of $400,000. The contractor has already spent $240,000, or 60% of the estimated cost. To keep this simple, assume the contractor measures progress using costs incurred divided by its current total-cost estimate.

Measure Illustrative amount
Contract price $500,000
Estimated total job cost $400,000
Cost incurred so far $240,000
Estimated completion percentage 60%
Illustrative value of work earned at 60% $300,000
Progress billed to date $250,000
Difference between work earned and billing $50,000
Estimated cost still to finish $160,000

In this simplified example, billing trails the estimated value of work performed by $50,000. That does not mean there is a $50,000 invoice available to finance, or that the customer owes that amount now. The contract, billing rules, accepted work and accounting policy determine what can actually be invoiced and recognized.

If the estimate of total cost rises to $450,000 while the work completed stays the same, the estimated completion percentage falls to about 53.3%. The report must be updated; otherwise the projected margin can look healthier than it is.

What should a contractor do before seeking financing?

Review every open job with the project manager and bookkeeper. Make sure billed amounts match the invoices, reconcile customer payments with the bank, identify unpaid holdbacks, and update the cost-to-complete estimate. Explain major gaps, disputed extras and contracts that may lose money. Bring current financial statements and a cash forecast showing when project bills fall due.

For accounting recognition and reporting, ask your accountant which standards apply to the business. Financial reporting for construction contracts is not identical to a simple job cash forecast. [2]

If you need help reviewing working-capital options while a project is under way, BGC can assess your financing request and explore possible routes. Lender requirements and available structures vary; a complete WIP schedule does not guarantee financing.

Related BGC guides: Running two jobs at once; Why bank deposits differ from sales; Accounts-receivable aging reports.

For an overview of financing options for construction businesses, see Business Financing for Construction Companies in Canada.