Cash flow and working capital

How much cash does a contractor need to run two jobs at once?

Learn to forecast cash for two overlapping construction projects rather than budgeting each job separately.

By
Alexander Schnavel
Reviewed by
Published
November 9, 2026
Last reviewed
Key points

A second job can be profitable and still leave your company short of cash. Before you accept it, place both jobs on one calendar. Show when wages, subcontractors and materials must be paid, and when each customer is likely to pay you. The amount you need is the lowest point on that combined calendar, plus a reasonable cash reserve. The total value of your contracts does not tell you how much money will be available next Friday.

Why does the second job change the answer?

Imagine that Job A is already underway. Its next progress payment is expected in three weeks. A new customer then offers Job B, which requires a crew and a material deposit next week. You may have enough profit in the two quotes, but the timing of the payments creates a new cash gap.

The invoices for Job A and Job B belong on separate job records. Your bank balance does not. Both jobs pay workers and suppliers from the same available money. That means the second job can use the funds you were counting on to finish the first.

Do not treat a certificate, progress invoice or completed milestone as cash already collected. Check what the contract says about approval, the date an invoice becomes payable and any holdback. These requirements vary by contract and province. In Ontario, for example, the Construction Act contains rules about holdbacks and payment timing, but its conditions should not be copied into a Quebec or Alberta project without checking the applicable rules. [1]

A four-week example with two projects

Suppose a contractor begins with $35,000 in available cash. Job A has a scheduled $45,000 customer collection in week 3. Job B has a scheduled $40,000 collection in week 4. The contractor expects the following combined new cash movements across the jobs. The amounts are invented to explain the method, not a forecast of typical costs or actual client results.

Week Customer cash collected Wages, materials and other job cash paid End-of-week cash before financing
Start — — $35,000
1 $0 $30,000 $5,000
2 $0 $38,000 −$33,000
3 $45,000 $28,000 −$16,000
4 $40,000 $24,000 $0

The lowest end-of-week balance is negative $33,000. If the owner wants to keep $12,000 available for other business expenses, the example points to a $45,000 liquidity planning need. That is not necessarily a loan amount or an approved financing offer. Any payments from the company's other customers, existing debts, taxes or financing expenses would change the number.

The example also assumes that collections happen before the end-of-week calculation. A wage withdrawal due Tuesday and a customer deposit arriving Friday can make the real low point worse. Build a daily cash view for the busiest weeks, not only a weekly table. Our working-capital sizing guide explains the larger forecasting method.

What must be checked before taking Job B?

Start with your contract dates: when each project starts, when work can be invoiced, who must approve it and when the customer is contractually due to pay. Then add committed cash costs: wages, subcontractors, deposits, rental charges, taxes and the part of your office costs paid from the same account.

Ask whether a progress payment from Job A can safely support Job B. That may seem reasonable if Job A has spare cash, but it is risky when Job A still has expensive work left to finish. Keep an estimate of costs to complete each job and compare it with payments still expected under that same contract.

Finally, test a delay. If Job A pays two weeks later than expected, can you still complete both projects without missing payroll? A forecast should show the date cash runs short and the most you may need, not just a statement that you have two signed contracts.

Could financing help cover the overlap?

A business line of credit may be worth comparing when shortfalls rise and fall as job payments arrive. Working capital financing may also be considered where a lender is satisfied that the company can afford its payments. Neither option is guaranteed, and availability depends on the lender's assessment, province, financial history, cash flow and other terms.

A loan does not fix a contract with too little margin. Before borrowing, see whether customers will agree to workable progress billing, whether suppliers will extend payment terms and whether Job B can begin later. Compare the amount and timing of repayments with the likely collections, using our payment frequency guide.

What should a contractor prepare?

Bring the two contracts or purchase orders, separate job budgets, expected completion costs, progress-billing terms, a combined daily or weekly cash calendar, current bank statements and details of existing debt payments. Ask the lender or broker to explain any security requirements, total repayment and what happens if a customer pays late.

If you are deciding whether to accept a second project, review BGC's eligibility guidance before applying. Better Growth Capital is a financing broker, not a direct lender; a lender makes the final credit decision.

For an overview of financing options for construction businesses, see Business Financing for Construction Companies in Canada.

Ready to explore your options?

Tell us about your business, your financing need and how you expect to use the funds. We'll help you understand potential next steps through our funding partners.